Renovating the Lawrence and Eris Field Building at 17 Lexington Avenue
Construction Schedule

Rendering of main lobby exterior
The proposed schedule for Phase IA of the construction schedule follows. Please check back for a link to the upcoming construction site, which will have real-time updates once construction begins:
| Activity | Schedule |
| Make Ready Projects | Winter/Spring 13 |
| Demo/Abatement | Fall/Winter 13 |
| Excavation/Foundation | Winter 13/Spring 14 |
| Superstructure | Spring/Summer 14 |
| Exterior Enclosures | Fall/Winter 14 |
| Interior Fit-out | Spring/Summer 15 |