Renovating the Lawrence and Eris Field Building at 17 Lexington Avenue

Construction Schedule

Rendering (exterior)
Rendering of main lobby exterior

The proposed schedule for Phase IA of the construction schedule follows. Please check back for a link to the upcoming construction site, which will have real-time updates once construction begins:

Activity Schedule
Make Ready Projects Winter/Spring 13
Demo/Abatement Fall/Winter 13
Excavation/Foundation Winter 13/Spring 14
Superstructure Spring/Summer 14
Exterior Enclosures Fall/Winter 14
Interior Fit-out Spring/Summer 15

 

Download the Construction Management overview PDF